(i) the status of work done on the above roads in terms of the percentage of completion of the construction;
view
-
31 Jul 2014 in National Assembly:
ii) circumstances under which works on the said roads have been delayed; and,
view
-
31 Jul 2014 in National Assembly:
iii) the expected date of completion of the construction of the above roads.
view
-
31 Jul 2014 in National Assembly:
Hon. Speaker, I beg to answer as follows:-
view
-
31 Jul 2014 in National Assembly:
(i) The Sotik-Cheplanget-Cheborgei-Roret-Sigowet Road Project was awarded to M/s Spencon Kenya Ltd at a contract sum of Kshs.3,149,152,168.90. The scope of works is for improvement to bitumen standards of the 420-kilometre road. Out of this, the section between Sotik to Cheplanget - five kilometers - was done through force account and is completed to bitumen standards. The electronic version of the Official Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Hansard Editor.
view
-
31 Jul 2014 in National Assembly:
The Litein-Cheborgei-Kibugat Road section has been designed. The section of this road between Litein to Cheborgei - six kilometers - has been included in the contract for Sotik-Cheplanget-Cheborgei-Roret-Sigowet. This makes the total road under the contract for improvement to bitumen standards to be 48 kilometers. The section from Cheborgei to Kibugat will be considered later as funds become available. I want to report that this morning, I was with officers from the Ministry and they have also placed the remaining 15 kilometres under the annuity; the programme that the Ministry is undertaking. Even the 15 kilometres will be part of ...
view
-
31 Jul 2014 in National Assembly:
For the contracted road section, the overall progress of the work is at 47.8 per cent. The length of the road completed up to bitumen standard is 13 kilometres, inclusive of the section done through the force account.
view
-
30 Jul 2014 in National Assembly:
I am sorry, hon. Deputy Speaker. Could he repeat?
view
-
30 Jul 2014 in National Assembly:
Hon. Deputy Speaker, last week we dealt with all the Statements that were supposed to be dealt with by my Committee. Maybe the Clerk did not list that on the Order Paper. We will revisit the issue this week or next week so that we deal with your Statement.
view
-
23 Jul 2014 in National Assembly:
Hon. Deputy Speaker, we have a meeting tomorrow. The Member can attend because this is a straightforward question. He just wants to know the status of the road in this particular area. This can be answered tomorrow because we have the Cabinet Secretary and his team tomorrow. The Member can appear before the Committee tomorrow but; if he does not, then it will take one week to respond to him.
view