3 Aug 2011 in National Assembly:
Mr. Speaker, Sir, I have spoken to the hon. Member because I feel this answer is not sufficient for the Question asked by hon. Member. We are, therefore, requesting that this Question be deferred to next week.
view
-
3 Aug 2011 in National Assembly:
Much obliged, Mr. Speaker, Sir.
view
-
3 Aug 2011 in National Assembly:
Mr. Deputy Speaker, Sir, I beg to reply.
view
-
3 Aug 2011 in National Assembly:
(a) I am aware that the upgrading of Bumala-Port Victoria Road to bitumen standard has been done up to 35 kilometres. The remaining works are being implemented under a new project that includes other roads in the area.
view
-
3 Aug 2011 in National Assembly:
(b) I am aware that the tender for the completion of the road was advertised, adjudicated and the contract awarded to the winning bidder on the 27th May, 2011.
view
-
3 Aug 2011 in National Assembly:
(c) I wish to confirm that the contract has already been signed and the contractor is expected to be on site by the end of August 2011. The expected date of completion is the end of March, 2013.
view
-
3 Aug 2011 in National Assembly:
Mr. Deputy Speaker, Sir, I wish to confirm that we have been able to forward the deposit to the contractor. Therefore, there is no reason why he should not be able to start the work as planned. I also wish to confirm that the contract sum for the project is Kshs1,488,339,000. The sections to be covered under this contract include the remaining section of D251, that is, approximately 13.9 kilometres long, and two, from Manyasi Junction to Bunyala District Headquarters in Rwamba; that is, Road E1201, and is approximately six kilometres long. Then we have Road C30, the junction to ...
view
-
3 Aug 2011 in National Assembly:
Mr. Deputy Speaker, Sir, as I have indicated, we expect the contract to start at the end of August this year and will go on until March 2013. We have not factored in all the money, but we have factored in all the money that is required for the contract to start. As you are aware, it will end in 2013.
view
-
3 Aug 2011 in National Assembly:
Mr. Deputy Speaker, Sir, indeed, I want to confirm that what the hon. Member has stated is correct. I also wish to state that, initially, we would have wanted to include that portion as part of the project, but we were not able to include it in this particular contract due to financial constraints. However, I want to assure the hon. Member that we will be able to prioritise it as soon as we get the necessary allocations for it.
view
-
3 Aug 2011 in National Assembly:
Mr. Deputy Speaker, Sir, I am afraid that is an entirely different Question. I do not have the details on that particular section of the road now, but given time, I will be able to table that information before this House.
view